Welcome to the DMK Development Update Page for 

Winder, GA – Charter Senior Living

If you have any questions about this project, please contact us at 502-423-0662

Week of 10/23/2026

KEY DATES & LOOK-AHEAD

Activity / Milestone Date Status
Projected Certificate of Occupancy December 2026 On track

HIGHLIGHTED WORK THIS WEEK

  • Elevator installation continued this week, along with kitchen equipment and installation of the rooftop HVAC unit.
  • Balcony rails remain in fabrication and are scheduled for installation on October 26.

WORK ACTIVITIES BY SITE AREA

SITEWORK / EXTERIOR

  • Site light pole installation continued.
  • The siding crew continued installing Hardie board material.

BUILDING INTERIOR

  • Final painting, trim and hardware, vinyl plank flooring, and ceramic tile installation all continued this week. Carpet installation continued in the Floor 2 units of Phase A, and countertop setting continued on Floors 1–3 in Phases A & B. Drywall crews continued finishes and touch-ups in Phase A. Final painting will continue next week.
  • Plumbing finishes continued in Phases A and B, and electrical finishes continued in the common areas. HVAC crews continued finishes and installation of rooftop units, PTACs, and VTACs.

WEATHER

No weather delays were reported this week.