Home  |  WINDER WEEKLY UPDATE

WINDER WEEKLY UPDATE

Welcome to the DMK Development Update Page for 

Winder, GA – Charter Senior Living

 

If you have any questions about this project, please contact us at 502-423-0662

Week of 07/24/2026

SCHEDULE UPDATE: Plumbers, HVAC, electricians, and sprinkler contractors passed state fire and city inspection in Area C, level 2. Ready for insulation. Electricians continue to make up panels. Drywallers have completed taping and finishing Area C level 3; also completed soffits in Area B level 1 and 2. Unit trim to start level 3 Area C 7/24. Paint primer is in progress in Area C level 3. Brick masons continue installing brick on the entire building; approximately 80% complete. Storefront doors and windows are installed. Siding has started with soffit and fascia installation. Balcony decking is complete.

PROJECTED CO: 11/26

PROGRESS NOTES BY TRADE:  

  1. Plumbers: Completed rough-in Area C.
  2. HVAC: Completed rough-in Area C.
  3. Electrical: Continue rough-in Area C level 1.
  4. Sprinkler: Rough-in soffits throughout.
  5. Masonry: Brick install at ground level over 90% of the building, including starting on level 2 balconies, approaching 80% complete.
  6. Access Control: Rough-in complete.
  7. Drywall: Tape and finish level 3 area C complete; install hat channel and RC channel levels 1 and 2 area C. Soffit drywall install started.
  8. Low Voltage: Rough-in for speakers and cameras complete.
  9. Cabinets: Area A levels 2 and 3 install complete.