SCHEDULE UPDATE: Plumbers, HVAC, electricians, and sprinkler contractors passed state fire and city inspection in Area C, level 2. Ready for insulation. Electricians continue to make up panels. Drywallers have completed taping and finishing Area C level 3; also completed soffits in Area B level 1 and 2. Unit trim to start level 3 Area C 7/24. Paint primer is in progress in Area C level 3. Brick masons continue installing brick on the entire building; approximately 80% complete. Storefront doors and windows are installed. Siding has started with soffit and fascia installation. Balcony decking is complete.
PROJECTED CO: 11/26
PROGRESS NOTES BY TRADE:
![]()
![]()