SCHEDULE UPDATE: Wood framers continued final punchout work. Metal framers continued setting trusses in Areas B and C as well as quality checks, punchout work, and roof sheathing. Plumbers and HVAC received rough-in inspection for 1st floor of Area A and continued rough ins of 2nd floor Area A. Sprinkler subcontractor received rough-in inspection for first floor in Area A and continued rough ins in Area B and 2nd floor of Area A. Electricians wrapping up rough ins in Area A and starting in Area B. Paving contractor completed first coat of paving on front half of the parking lot. Charter sales trailer was delivered.
PROJECTED CO: 12/2026
PROGRESS NOTES BY TRADE:
![]()
![]()
![]()
![]()
![]()
![]()
![]()
![]()