Schedule Update: Metal framing is working on 2nd floor wall installation continuing area C, with 3rd floor joist continuing as well in area C as well. Wood framing continues to work on 2nd floor walls in area C and start 2nd floor walls Area B. Concrete sub is continuing with curb and gutter installation in front of building on both sides of the Porto cochere.Ā Steel sub completed the installation of the steel hangers for the wood farmers and continued installation for metal framing to continue at structural steel supports.
Ā PROJECTED CO: 11/2026
PROGRESS NOTES BY TRADE:Ā Ā
![]()
![]()
![]()
![]()
![]()