Welcome to the DMK Development Update Page for 

Portage, MI – Trilogy Health Services

If you have any questions about this project, please contact us at 502-423-0662

 

Week of 10/23/2026

SCHEDULE UPDATE: A measured week on site, but with noticeable and meaningful progress! The painter kicked off corridor painting, bringing a fresh, finished look to those high-visibility spaces. The electrical crew continues to button up common area light fixtures, with the building’s interior coming together more visibly by the day. Epoxy flooring hit a brief delay due to a material backorder, but the team is prepped and ready to hit the ground running as soon as materials are in hand next week.

PROJECTED CO:  11/27/26

PROGRESS NOTES BY TRADE:

  1. Electrical – Miscellaneous common area lighting.
  2. Plumbing – Off site until finishes.
  3. Fire Suppression – Off site.
  4. Low Voltage (Network Fire) – Nurse call and fire alarm rough’s.
  5. Low Voltage (360 Network) – Off site.
  6. Insulation – N/A
  7. Drywall – Common area patching/finishing. Egress hall framing/drywall.
  8. Paint – Corridor painting and 400 Wing phase 1 door hold open patches.
  9. Finish Carpentry – Kitchen cabinet installation ongoing.
  10. Flooring – Bathroom floor prep in apartments completed.
  11. Paving – Complete.
  12. Concrete – Complete.