SCHEDULE UPDATE: A measured week on site, but with noticeable and meaningful progress! The painter kicked off corridor painting, bringing a fresh, finished look to those high-visibility spaces. The electrical crew continues to button up common area light fixtures, with the building’s interior coming together more visibly by the day. Epoxy flooring hit a brief delay due to a material backorder, but the team is prepped and ready to hit the ground running as soon as materials are in hand next week.
PROJECTED CO: 11/27/26
PROGRESS NOTES BY TRADE: